Skip to main content

Washington Avenue repaving and improvement project


A Complete Streets project

Washington Avenue repaving and improvement project timeline

2013

Community outreach begins and continues through 2015.

2016

Analysis begins for parking, loading, and traffic operations. It continues through 2019.

2020

Community outreach efforts are adapted to meet COVID-19 social distancing requirements. Outreach includes online surveys, mailed postcards, online meetings, and videos.

The City announces the survey results and preferred design option.

2021

The street paving schedule is moved to 2022. Additional community discussions take place, including conversations with a working group.

2022

Repaving begins on Washington Avenue.

2023

Repaving is completed on Washington Avenue.

New parking and loading regulations are implemented on Washington Avenue.

Data collection begins for the Year 1 project evaluation.

2024

The City publishes the results of the Year 1 project evaluation.

Data collection for the Year 2 project evaluation is anticipated.


Top