Street Resurfacing Work – April 21st to 25th
1st, 2nd, 3rd, 5th, 6th Highway Districts
Check for posted parking restriction signage for updates
PHILADELPHIA – The Department of Streets announces roadway work will begin next week, April 21st to April 25th, on the following streets:
1st and 2nd Highway Districts:
On Street | From Street | To Street |
Jackson St | S 17th St | S 18th St |
S 17th St | Ritn St | Oregon Ave |
S 23rd St | Ritn St | Wolf St |
Mifflin St | S Broad St | 25th St |
Moore St | S 27th St | S Douglas St |
Saybrook St | S 52nd St | S Wilton St |
Latona St | S 60th St | S 61st St |
Washington Ave | Cobbs Creek Pkwy | S 62st St Or S 61st St |
Walton Ave | S 61st St | S 60th St |
Pemberton St | S 59th St | S 56th St |
Catharine St | S 56th St | S 50th St |
3rd Highway Districts:
On Street | From Street | To Street |
B St | Allegheny Ave | Tusculum St |
B St | Tusculum St | Somerset St |
B St | Lehigh Ave | Gurney St |
Somerset St | B St | Tusculum St |
Tusculum St | A St | Somerset St |
Kip St | Cambria St | Tusculum St |
C St | Allegheny Ave | Indiana Ave |
C St | Indiana Ave | Cambria St |
C St | Tusculum St | Somerset St |
D St | Allegheny Ave | Clearfield St |
Rorer St | Allegheny Ave | Clearfield St |
F St | Allegheny Ave | Clearfield St |
Indiana Ave | Kensington Ave | Boudinot St |
Rorer St | Indiana Ave | Cambria St |
Indiana Ave | From Street | Tusculum St |
Hope St | Indiana Ave | Clearfield St |
5th and 6th Highway Districts:
On Street | From Street | To Street |
Unruh Ave | Torresdale Ave | Frankford Ave |
Magee Ave | Torresdale Ave | Frankford Ave |
Gaul St | Lefevre St | Casimir St |
Casimir St | Gaul St | Belgrade St |
Belgrade St | Orthodox St | Lefevre St |
Wilmot St | Almond St | Belgrade St |
Almond St | Orthodox St | Lefevre St |
Edgewood St | Lefevre St | Orthodox St |
Salmon St | Lefevre St | Berkshire St |
Plum St | Richmond St | Salmon St |
6th Highway District:
On Street | From Street | To Street |
Avalon St | Academy Rd | Berea St |
Berea St | Avalon St | Chesterfield Rd |
Avalon St | Avalon St | Dead End |
Lavender St | Avalon St | President St |
President St | Academy Rd | Outlook St |
Legion St | Avalon St | President St |
Outlook St | Avalon St | President St |
President St | Outlook St | Berea St |
Berea St | President St | Glenn St |
Glenn St | Berea St | Lavender St |
Lavender St | Glenn St | President St |
Lavender St | Glenn St | Dead End |
Legion St | President St | Glenn St |
Legion St | Glenn St | Dead End |
Glenn St | Lavender St | Academy Rd |
This work will happen in four phases: Milling, Prep, Paving, and Line Striping. Phase one, crews milling the roadway will remove the old asphalt surface. Phase two, additional prep work such as adjustments to utility access and manhole covers is conducted. Phase three, paving crews will resurface the street. Phase four, line striping crews will paint stop bars, crosswalks, and other lines as designed.
These four phases are completed by different crews on different days. Please pay attention to posted signage for updates on when work will occur and parking will be restricted. If your vehicle is relocated, check nearby streets or contact your local police district. A map of police districts can be found online at: www.phillypolice.com/district/district-gis